Upgradation of Tirupati Railway Station to be completed by Feb, 2025
Tirupati, Feb 7
The upgradation work of Tirupati Railway Station to cater the needs of the rail passengers for the next 40 years is proceeding at brisk pace and is scheduled to be completed in two years
The South Central Railway (SCR), which started the upgradation work in May 2022, said on Tuesday that the work is being monitored at all levels so as to ensure timely completion of the project. The work has been awarded under EPC mode and the entire project is targeted for completion by February, 2025.
A new station building is coming up on the South side of the existing station building. After completion of geological survey, setting-up of camp office, concrete lab and storage sheds, remaining works have continued to move in a fast manner.
The concreting of the foundations has been completed 100 per cent for the new upcoming station building. Till date, about 7,450 cubic meters of concrete has been used in foundations, columns of basement floor and retaining wall.
The SCR said in the next phase, work related to centering and shuttering of the concrete slab for the basement floor has commenced and is progressing briskly. As on date, almost 20 per cent of the work has already been completed. An underground water tank with a capacity to hold 29 litres of water is to come up as part of the new station building. For this, both excavation works for construction of underground tank as well as concreting of its foundations has also been completed.
Two new air concourses are planned to be constructed as part of the upgraded station to handle both incoming as well as outgoing passenger passengers. These air concourses will be of 35 meters width and will connect all the platforms of the station and also both sides (North as well as South) of the Station buildings.
Arun Kumar Jain, General Manager, SCR stated that the upgradation works of Tirupati station are being monitored regularly so that the work is not hampered and it is completed within the targeted time. He also stated that the works are taken up with utmost caution to ensure least inconvenience to the passengers and train movements in the station.
3 minutes ago
Trump should address Beijing’s ‘ethnic unity law’ during meeting with Chinese President
4 minutes ago
'Gyanesh Kumar should turn approver': Rahul Gandhi reiterates demand of CEC's resignation
8 minutes ago
Yami Gautam celebrates family legacy of handloom craftsmanship in black Maheshwari saree
13 minutes ago
Asian Games: Seema Kumari claims bronze in women’s 10,000m, ends India’s 16-year wait
35 minutes ago
‘Agadha’ Brings a World of Mystery, Faith and the Supernatural to ZEE5 on September 25
49 minutes ago
US says can help energy security of partners affected by Russia oil tariff law
50 minutes ago
US lawmakers call on Trump to press Xi on soybean, beef trade issue
51 minutes ago
US Bill to bar China-linked cars gains support
52 minutes ago
CARICOM ministers vow Caribbean community's support to India's candidature for UNSC 2028-29 term
2 hours ago
Exercise Yudh Abhyas: US envoy Gor arrives in Rajasthan, says looking forward to seeing troops train side by side
2 hours ago
OpenAI Agent 'Infiltrated' Australian Government Website, Prime Minister Anthony Albanese Says
2 hours ago
Do Popular GLP-1 Drugs Like Ozempic, Wegovy, and Mounjaro Cause Permanent Vision Loss? Hundreds of Lawsuits Spark Safety Debate
4 hours ago
Adani Group to invest over Rs 1,00,000 crore in West Bengal by 2035: Gautam Adani