Indo-Bangla joint venture Rampal plant to resume power production from Wednesday
Dhaka, Feb 15
Rampal power plant, a joint venture of Indian state-owned NTPC and Bangladesh Power Development Board (BPDB), will resume its operations from Wednesday.
Unit-1 of the plant, having 660 MW capacity, was forced to shut down on January 14 due to shortage of coal. The authorities of the power plant were unable to open any letter of credit (LC) to import coal due to the dollar crisis.
After a lot of persuasion at the policy level, LC-opening was allowed for importing coal and the supplier sent a consignment of 30,000 metric tonnes, said Anwarul Azim, deputy general manager of the Bangladesh-India Friendship Power Company Limited (BIFPCL).
"The imported coal reached the jetty of the power plant on February 9 and now we are set to resume operation at the unit-1 of the plant from Wednesday," he said.
Azim said the first unit started supplying electricity to the national grid on a trial basis on December 18, 2022 night.
Azim further said 79.35 per cent of the work of the second unit has already been completed. If everything goes according to plan, work of the second unit with a production capacity of 660 MW will be completed soon. He hoped the second unit would start commercial production in June.
BIFPCL officials said that State Minister for Power, Energy and Mineral Resources Nasrul Hamid is expected to visit the plant on Thursday.
The unit is ready to go into commercial production, Bangladesh Power Development Board (PDB) spokesperson Shameem Hasan told media.
The first unit of the 1,320MW power plant in Bagerhat is supplying 620-630 megawatt of electricity to the national grid per day through the Mongla-Mawa-Aminbazar gridline of Dhaka.
"The authorities are yet to fix the date for starting commercial operation. A committee comprising officials of the power ministry, the PDB and Power Grid Company of Bangladesh (PGCB) will inspect the power plant and fix the date soon," he mentioned.
The official said that another consignment of 50,000 MT of coal is also coming to the country soon. He also informed that the plant's unit-2 is expected to be operational from June this year.
27 minutes ago
Lisa Ray expresses heartbreak after airstrikes hit Lebanon: My adopted second home
2 hours ago
Lebanon not part of US-Iran truce deal: Israeli envoy
5 hours ago
White House confirms talks in Islamabad, VP Vance to lead US delegation
6 hours ago
Bismil Ki Mehfil: Ignites North America with Divine Rhythms, Qawwali Passion, and Electrifying Fusion
6 hours ago
ZEE5 Drops ‘Everybody Loves Sohrab Handa’ Trailer; Streams April 10
6 hours ago
Kajol wishes birthday to the 'classy gal' Jaya Bachchan as she turns 78
6 hours ago
Mukesh Khanna blasts Samay Raina over ‘Shaktimaan’ comment in show: 'Woh roasted praani hai'
6 hours ago
Aditya Rikhari says ‘it’s personal, honest on song ‘Tu Jahaan’ from ‘Dacoit’
6 hours ago
Shabir Ahluwalia ‘flirts with trouble’ in playful mirror selfie with wife Kanchi Kaul
6 hours ago
Suchitra Krishnamoorthy opens up on losing parents, siblings in the past few years: Nazar Lag Gayi
6 hours ago
Somy Ali recalls being pitted against Henna actress Zeba Bakhtiar in the 90s
6 hours ago
Kritika Kamra: Was sure that I won’t take a long break pre and post wedding
6 hours ago
ECI hosts 23-nation delegation in Kerala to witness voting process