After 10 days’ woes for commuters, WR readies 6th line between Goregaon-Khar
Mumbai, Nov 6
The Western Railway (WR) has completed a critical piece of infrastructural work – the 6th line on the 8.8-km-long Goregaon-Khar stretch – of the congested Mumbai suburban section, an official said on Monday.
The sixth line, which will help divert all long-distance trains in both directions to clear the suburban section, was completed after 10 days efforts at 6 stations, entailing cancellation of several hundred services daily that had proved a veritable torture for the commuters.
WR chief spokesperson Sumit Thakur said that the speed trials of 112 kmph were achieved on this new line, and now all the suburban services have been restored from Monday.
The entire work involved laying 12 turnouts and three trap-points on the existing 5th line and both the fast corridors in up and down directions.
It also saw laying of 8 turnouts on the new line and dismantling of existing 9 turnouts and 3 trap points from the existing lines.
Now, an independent connectivity to both the 5th and 6th lines has been provided with the Bandra Terminus Yard after slewing of 700-metres existing tracks and dismantling of five points including a diamond crossing.
During the huge works, the WR had deployed heavy machinery at various locations like T-28, UNIMAT, Duomatic, UTV, hydraulic cranes, JCBs, etc to complete the work smoothly, said Thakur.
For the entire project, the WR has acquired government and private land, and built new 27 foot over bridges to replace existing FOBs that were infringing the alignment.
Thakur said existing railway structures that obstructed the 6th line were dismantled and new were built in their place, including 192 flats in the railway quarters, six new electronic interlocking buildings, two new traction sub-stations, three booking offices, etc.
In this effort, 607 project affected persons were rehabilitated in alternate homes, and around 1,000 trees were relocated and transplanted. Now, the work will start on extending the 6th line between Goregaon to Borivali that is likely to be completed mid-2024.
Thakur said that the new 6th line will enhance the capacity of Mumbai suburban section by adding more train services and also improve punctuality.
3 hours ago
Malabar Gold & Diamonds Proudly Represents India’s Global Business Vision at PM Modi’s ‘Kia Ora Modi’ event in Auckland, New Zealand
3 hours ago
Didi Krishna’s Message to Physicians at AAPI Convention 2026: A Sacred Blueprint for Physicians as Healers
3 hours ago
Deeply disappointed: 'Melbourne Meets Modi' organisers on 'paid crowd' claims of Rahul, Kharge; seek apology
4 hours ago
‘This is just the beginning’: Tendulkar hails landmark Lord’s Test as defining moment for women’s cricket
4 hours ago
Successive reports on presence of foreign operatives in and around India raises serious concern
8 hours ago
India strongly condemns the attack on vessels transiting Strait of Hormuz
9 hours ago
Devi Sri Prasad on S Janaki amma: Words cannot justify the greatness of this legend!
9 hours ago
Boney Kapoor on daughter Anshula's wedding: ‘It's a memory i'll carry forever’
9 hours ago
Mugdha Godse opens up about her small contribution to Marathi film 'Frame'
9 hours ago
S Janaki's granddaughter Apsara Vydyula: Don’t measure my love for my grandmother by the tears you do or do not see!
9 hours ago
Actress Bhavana clarifies that she does not have a Facebook account!
9 hours ago
Ajay Devgn looks back at 20 years of ‘Golmaal’, calls the journey full of unlimited fun
9 hours ago
Krystle D’Souza calls Awakenings 2026 a core memory, says she’s ‘ruined for every other festival now’