Centre tells states to meet guidelines for ensuring adequate power to consumers
New Delhi, Feb 12
Union Ministry of Power has sent a detailed letter to all states and union territories for adherence to “Resource Adequacy Guidelines” in order to ensure adequate growth in the nation’s power capacity in line with the rapidly growing electricity demand.
The letter states that as per the Resource Adequacy (RA) Guidelines, the distribution licensees are mandated to prepare RA Plan for a 10-year horizon (on a rolling basis) to meet energy requirements.
“It is imperative that all States and UTs must complete their Resource Adequacy Plans for the period starting 2024-25 to 2033-34 in accordance with the rules and guidelines. It is required that all distribution licensees tie up enough capacity for a round-the-clock power supply,” the letter reads.
It states that as on date "Resource Adequacy (RA) Studies" up to the year 2031-32 have been completed by the Central Electricity Authority (CEA), for 23 States/UTs, while the RA studies are in progress for the rest of the States and UTs, namely for Delhi, Goa, Sikkim, Haryana, Bihar, West Bengal, Chandigarh, Puducherry and J&K.
“However, the distribution licensees are now required to submit to CEA the data up to the year 2033-34, for carrying out national-level RA studies. Accordingly, a detailed letter dated 2nd February, 2024 has been sent to the states and UTs, for adherence to Resource Adequacy Guidelines,” the letter points out.
It reads that the Rule10 of the Electricity (Rights of Consumers) Rules, 2020 states that distribution licensees must provide power to all customers round-the-clock, with the exception of a few consumer categories for which the State Electricity Regulatory Commission has set lower supply hours.
“The Indian economy is expected to keep growing at a high rate and become the third-largest economy of the world by the year 2030. As a result, our power consumption has also surged, with the peak power demand rising by more than 79 per cent, from 136 GW in 2014 to 243 GW today,” the letter reads.
It reads that correspondingly, our generation capacity has also expanded, rising from 248.5 GW in March 2014 to 428.3 GW in December 2023, a 72.4 per cent increase.
“Additionally, the nation has installed adequate inter-regional transmission infrastructure to move 117 GW of power across the nation,” the letter reads.
It adds that to cater to the rapidly growing demand, it is imperative that the country's generation capacity also develops at an accelerated rate.
1 hour ago
16-year-old girl gang-raped and killed in Delhi, body found in field
1 hour ago
30 lakh beneficiaries registered under PM Vishwakarma scheme: Minister
1 hour ago
Mayawati opposes proposed UPI charges, says additional burden will hit common people
1 hour ago
NTA releases final answer keys for UGC-NET June 2026 exam in English, Commerce and Sociology
1 hour ago
PM Modi’s cleanliness campaign has evolved into people’s movement: Arunachal CM Khandu
1 hour ago
EAM Jaishankar meets King of Bhutan, values his guidance to deepen ties
3 hours ago
“Those spreading this hate need to stop”: US Congressman Raja Krishnamoorthi condemns stabbing of Sikh truck driver in Wyoming
3 hours ago
UNGA votes to allow Palestine head address high-level meet via video link after US denies visa
3 hours ago
US secures American’s release in Myanmar
3 hours ago
US sanctions Cuba’s nickel, military network
3 hours ago
Trump signs orders to widen hunting, fishing
3 hours ago
Pentagon orders testosterone checks for troops
3 hours ago
US lawmakers urge Trump to press China on detained Americans, AI chips ahead of Xi meeting